There are a total of 354 Commitments currently in the database. We are displaying up to 15 at a time.
Invest J$100M to erect greenhouse/water harvesting sites across all five bauxite-bearing parishes
Actions Taken
12 sites earmarked for 1.2M in four parishes.
Related Articles
No articles on record

Launch Castor Bean Project to utilize thirty acres of mined-out bauxite lands to cultivate Castor plants
Actions Taken
Delayed due to financial constraint.
Related Articles
No articles on record

Install J$10M worth of solar street lights in rural bauxite communities
Actions Taken
Not implemented due to security concerns.
Related Articles
No articles on record

Begin implementation of Lydford Estate project to build 500 housing units
Actions Taken
PIAB approved the concept. Construction to commence in 2026.
Related Articles
No articles on record

Commence Phase 4 of Reynolds Pier PAJ/JBM development plans
Actions Taken
Completed Phase 4.
Related Articles
No articles on record

Deliver 300 titles
Actions Taken
294 titles delivered.
Related Articles
No articles on record

Establish a geoscience institute
Actions Taken
No document available*.
Related Articles
No articles on record

Implement geo-fencing technology
Actions Taken
Not Implemented due to lack of technology and infrastructure requirements.
Related Articles
No articles on record

Implement electronic testing of Provisional Drivers licence applicants at five depots
Actions Taken
Not Implemented due to lack of technology and infrastructure requirements.
Related Articles
No articles on record

Extend digitization operations seven additional Examination Depots
Actions Taken
Not done.
Related Articles
No articles on record

Establish a Chief Investigative department to receive and investigate complaints
Actions Taken
Unit established and operational.
Related Articles
No articles on record

Begin revision of the Transport Authority Act and the Road Traffic Regulations
Actions Taken
Transport authority Act passed; Regulations amendment in progress.
Related Articles
No articles on record

Finalize procurement of 50 new buses and 20 CNG buses
Actions Taken
Procurement completed for 50 new buses and 6 CNG buses.
Related Articles
No articles on record

Implement a maritime single window to facilitate the electronic clearance of ships
Actions Taken
Consultation held with stakeholders. Phase 1 to commence in 2024.
Related Articles
No articles on record

Develop a new model of the Jamaica Ship Registry
Actions Taken
The mangement and operation bid failed.
Related Articles
No articles on record