Auditor General's Findings

For the period April 2013 to March 2014, we identified 35 payments totalling approximately $15.62 million made to a supplier for the provision of meals to police personnel and prisoners in St. James. However, there was no evidence that a written contract existed between the JCF and the supplier outlining the terms and conditions under which the meals were to be provided.

We found no evidence that a competitive process was used to engage the supplier neither was there any evidence of endorsement from the National Contracts Commission (NCC) in keeping with the requirements of the Government of Jamaica Handbook of Public Sector Procurement Procedures at that relevant time. The JCF was also not able to provide any proof that the supplier was tax compliant and registered with the NCC.

Responsive image

Permanent Secretary (current): Dianne McIntosh

Breach Category: Procurement & Contract Management

Permanent Secretary (at breach):

Breach Type: Noncompliance with Procurement Guidelines

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments

Most Recent Breaches

MOEYI – Over $483 Million in Procurement Not Informed by Needs Assessment

April 11, 2022 | No comments

View Breach »

MSET- Poor decision-making costs Petrojam in excess of $67 million for a fence.

April 11, 2022 | No comments

View Breach »

MSET – Deficiencies in Petrojam’s Human Resources Management Practices

April 11, 2022 | No comments

View Breach »

MLSS – $2.95 Billion in Outstanding NIS Contributions

April 23, 2021 | No comments

View Breach »

HEART/NSTA – $75 Million disbursed without Compliance Checks

April 22, 2021 | No comments

View Breach »
0
Would love your thoughts, please comment.x
()
x