Auditor General's Findings
The 2023/2024 Auditor General’s Annual Report (subsections 3.2.56–3.2.65) Project) covered the audit of the Integrated Water, Land and Ecosystems (IWEco) Project for the four-year period ended December 31, 2022. The Project is financed by a US$3.114 million grant from the United Nations Environment Programme (UNEP) under the Global Environment Facility (GEF), co-financed by US$10.343 million from various agencies, with counterpart funding of US$43.8 million from the Government of Jamaica. The grant was to be disbursed over four years from May 31, 2018, but UNEP approved an extension of the completion date to September 30, 2024 to facilitate completion of Project activities.
The audit disclosed that the Project’s accounts were properly maintained, with expenditure transactions supported by adequate documentation and incurred in accordance with the Grant Agreement’s objectives and GoJ guidelines. Notwithstanding, National Environment and Planning Agency (NEPA), as the implementing Agency, was encouraged to address inadequacies in the management of its logical access controls to ensure compliance with the GoJ IT Security Policy and to strengthen network and application security to prevent exposure of NEPA’s financial information.
At December 31, 2022, NEPA had completed only 16 of 45 project activities and utilized US$1.1 million (36.67%) of the grant fund since the Project’s implementation in 2018. A further 5 activities had not been started, 9 were in progress, and 15 were discontinued. Due to implementation delays, the completion date was extended in three separate instances from its original end date of May 31, 2021 to September 30, 2024, and following a UNEP peer review, the Project was rescoped to 6 activities to ensure completion within the extended timeline.
The slow implementation was attributed to the resignation of the Project Officer, delays in filling that position and other key posts (impacting contract execution), and slippages of up to two years attributed to the COVID-19 pandemic, a lengthy procurement process, and the 18 months taken to complete the UNEP peer review (3.2.62). The AG noted that these delays increased the risk of the Project not achieving its intended objectives within the agreed timeline, and increased the risk of losing grant funding, which would in turn place greater reliance on the Consolidated Fund to complete outstanding activities.

Permanent Secretary (current): Arlene Williams
Breach Category: Project Management
Permanent Secretary (at breach): Arlene Williams
Breach Type: Inadequate Project Monitoring




