NWC – Poor Procurement Leading to Millions in Increased Costs

Share This:

Auditor General's Findings

The Auditor General’s Department undertook a Performance Audit of the National Water Commission’s Contract and Procurement Management of Capital Projects in 2017.

Most notably from the report, the AuGD found deficiencies in the scoping, execution and monitoring for 17 contracts, valued at J$1.8 billion and US$38.6 million, which resulted in increased costs of J$667 million and US$6.2 million respectively. These contracts did not meet the stipulated deadlines and resulted in an estimated combined time overrun of 126 months.

The AuGD also noted instances where contracts secured directly using the Emergency Contracting Methodology, did not commence until over a year after the contract engagement. This was contrary to expectations for emergency contracts and could have suggested an intent to circumvent GoJ’s Procurement Guidelines.

In addition, the NWC did not always scope projects and execute contracts in a timely manner, despite its financial constraints and responsibility to stakeholders. NWC incurred increased costs totalling $111.5 million for five projects and did not always rectify environmental concerns on a timely basis as required by citizens or stipulated by the Court.

Further, NWC’s monitoring of capital projects was not always effective, as in some instances, work was either rejected at the end of contract periods for failure to meet the required standards or were found to be incomplete. Of the contracts reviewed, the AuGD found instances of inadequate monitoring and oversight resulting in missed deadlines, incomplete works and increased costs.

Responsive image

Permanent Secretary (current): Audrey Sewell

Breach Category: Procurement & Contract Management

Permanent Secretary (at breach):

Breach Type: Poor procurement planning

Subscribe
Notify of
guest
0 Comments
oldest
newest most voted

Most Recent Breaches

Manchester MC – Outstanding 2023/2024 Financial Statement

July 14, 2026 | No comments

View Breach »

CMC – Eight Outstanding Financial Statements (2016/2017–2023/2024)

July 14, 2026 | No comments

View Breach »

SJMC – Unsupported $4.79B Revenue and $4.99B Expenditure; Five Outstanding Financial Statements

July 10, 2026 | No comments

View Breach »

STANNMC – 15 Outstanding Financial Statements Spanning 2009/2010 to 2023/2024, the Largest Backlog of Any Local Authority

July 10, 2026 | No comments

View Breach »

NEPA – IWEco Project: Delayed Implementation of Project Activities

July 8, 2026 | No comments

View Breach »
$3 TRILLION+
not accounted for

HELP US HOLD OUR GOVERNMENT AND PARLIAMENT TO ACCOUNT!

Governance is too important to be left solely to our politicians. Send a letter to your MP and to the Parliament letting them know where you stand.

This site uses cookies to give you the best online experience. By using our site you agree to accept these cookies. Read more about it here.

0
Would love your thoughts, please comment.x
()
x