Actions Taken

The actual expenidture for the works and services procured for the upgrade was $75,263,692.73.

 

Related Articles

https://tef.gov.jm/inprogress_project/devon-house-projects/

 

Actions Taken

Established two strategic partnerships for each project.

 

Related Articles

No articles on record

 

Actions Taken

Road rehabilitated.

 

Related Articles

No articles on record

 

Actions Taken

Delayed due to the realignmnet of the town and roads in St. Thomas.

 

Related Articles

No articles on record

 

Actions Taken

Completed 85% of design.

 

Related Articles

No articles on record

 

Actions Taken

Submitted plan for tender but the procurement excerises were unsuccessful.

 

Related Articles

No articles on record

 

Actions Taken

Not finalized. Delayed due to the pandemic and procurement challenges.

 

Related Articles

No articles on record

 

Actions Taken

Completed work at a cost of $20,581,340.00.

 

Related Articles

No articles on record

 

Actions Taken

Launched initative on September 30, 2022.

 

Related Articles

No articles on record

 

Actions Taken

Travel insurance initiative discontinued.

 

Related Articles

No articles on record

 

Actions Taken

The academy is in design phase. Concept design and Tourism Ecosystem Study completed.

 

Related Articles

No articles on record

 

Actions Taken

Completed 81% of the project; expended $168,371,407.83.

 

Related Articles

No articles on record

 

Actions Taken

Commenced architectural designs and completed the concept designs for $13,540,429.22.

 

Related Articles

https://jamaica-gleaner.com/article/business/20240324/hip-strip-be-redesigned-new-look | https://jamaica-gleaner.com/article/news/20221017/mobays-hip-strip-undergo-1-billion-transformation

 

Actions Taken

Fourteen beaches developed.

 

Related Articles

No articles on record

 

Actions Taken

Beautification project paused.

 

Related Articles

No articles on record

 

Actions Taken

Project cancelled.

 

Related Articles

No articles on record

 

Actions Taken

Project completed at a cost of $40,347,860.51.

 

Related Articles

No articles on record

 

$3 TRILLION+
not accounted for

HELP US HOLD OUR GOVERNMENT AND PARLIAMENT TO ACCOUNT!

Governance is too important to be left solely to our politicians. Send a letter to your MP and to the Parliament letting them know where you stand.

This site uses cookies to give you the best online experience. By using our site you agree to accept these cookies. Read more about it here.