SAMC- $ $46,851,105.30 paid to Contractor without verification of work done

Share This:

Auditor General's Findings

A contract dated March 26, 2020, was entered into between the St. Ann 

Municipal Corporation and Rahim’s Cleaning & Trucking Limited, in the 

amount of $46,851,105.30. The contract was awarded by the Corporation 

utilizing the Single-source procurement methodology and based on the 

Agreement, the Contractor agreed to the execution of works in relation to 

the St. Ann Municipal Corporation Ocho Rios COVID-19 Sanitation & 

Cleaning Project. 

 

Rahim’s Cleaning & Trucking Limited was paid by the St. Ann Municipal 

Corporation, on June 23, 2020, the amount of $45,138,446.13, in keeping with the terms of the contract. 

Responsive image

Permanent Secretary (current): Marsha Henry-Martin

Breach Category: Project Management

Permanent Secretary (at breach): Marsha Henry-Martin

Breach Type: Inadequate Project Monitoring

Subscribe
Notify of
guest

0 Comments
oldest
newest most voted
Inline Feedbacks
View all comments

Most Recent Breaches

SAMC- $ $46,851,105.30 paid to Contractor without verification of work done

October 14, 2024 | No comments

View Breach »

SEMC – St Elizabeth Municipal Corporation financial statements outstanding

October 1, 2024 | No comments

View Breach »

DCS – Unidentified lodgments totalling $2.1 million

April 18, 2023 | No comments

View Breach »

Accountant General – Pension Payments Made Without Verifying Life Certificates

April 18, 2023 | No comments

View Breach »

Accountant General – Overpaid Dependents a total of $4.1 million

April 17, 2023 | No comments

View Breach »
0
Would love your thoughts, please comment.x
()
x

This site uses cookies to give you the best online experience. By using our site you agree to accept these cookies. Read more about it here.